MDOT bid results: Apr 10, 2026
3 calls, 3 with bids, $24,939,918 in low bids.
Call 01
Yazoo CountyPavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 49
Project NHPP-0008-04(085) / 108150304
State estimate $13,364,573 · low bid $11,992,377 (10.3% under the estimate)
| # | Bidder | Total bid | vs. low |
|---|---|---|---|
| 1 | APAC - Mississippi, Inc.Richland, MS | $11,992,377 | Low |
| 2 | Dickerson & Bowen, Inc.Brookhaven, MS | $12,986,222 | +8.3% |
| 3 | Superior Asphalt, Inc.Byram, MS | $13,287,636 | +10.8% |
Call 02
Lowndes CountyMill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the Alabama State Lin
Project NHPP-0011-03(088) / 108649301
State estimate $8,289,152 · low bid $9,095,742 (9.7% over the estimate)
| # | Bidder | Total bid | vs. low |
|---|---|---|---|
| 1 | Falcon Contracting Company, Inc.Columbus, MS | $9,095,742 | Low |
| 2 | APAC - Mississippi, Inc.Richland, MS | $9,734,492 | +7% |
Call 03
Copiah CountyAsphalt Overlay approximately 12 miles SR 28 from Jefferson County Line to 1 mile East of Sylvarena Road
Project SP-0013-01(017) / 109044301
State estimate $4,599,817 · low bid $3,851,799 (16.3% under the estimate)
| # | Bidder | Total bid | vs. low |
|---|---|---|---|
| 1 | Dickerson & Bowen, Inc.Brookhaven, MS | $3,851,799 | Low |
| 2 | APAC - Mississippi, Inc.Richland, MS | $4,026,215 | +4.5% |
| 3 | Southern Paving, LLCFoxworth, MS | $4,226,678 | +9.7% |
| 4 | Joe McGee Construction Company, Inc.Lake, MS | $4,660,243 | +21% |
| 5 | Superior Asphalt, Inc.Byram, MS | $4,745,215 | +23.2% |
| 6 | A J Construction, Inc.Flowood, MS | $4,995,426 | +29.7% |